Attorneys and Parties

Gamma USA, Inc.
Plaintiff-Respondent
Attorneys: Michael Catania

Pavarini McGovern, LLC
Defendant-Appellant
Attorneys: Skyler Santomartino

Brief Summary

Issue

Construction-contract dispute arising from a large Times Square hotel, retail, and theater renovation project, focusing on the scope of damages recoverable in a pass-through claim by a construction manager/general contractor against a subcontractor.

Lower Court Held

The trial court held that because the counterclaim was asserted solely on behalf of the owner, all recoverable damages were limited to the $3.6 million liquidated damages cap in the subcontract.

What Was Overturned

The appellate court overturned the ruling to the extent it applied the $3.6 million cap to all categories of damages, and instead limited dismissal only to claims for delay damages above $3.6 million and for consequential damages.

Why

Reading the Construction Management Agreement (CMA) and the subcontract together, the appellate court found that the cap applied only to the owner's delay damages, while the CMA separately waived only consequential damages. Neither agreement barred the owner's direct damages claims, except for delay damages above the cap.

Background

Times Square Hotel Owner, LLC (Owner) hired Pavarini McGovern, LLC as the construction manager/general contractor (General Contractor) under a Construction Management Agreement (CMA). The CMA imposed liquidated damages of $10,000 per day, capped at $3.6 million, for certain delays and made that remedy the owner's sole remedy for delay damages. It also contained a mutual waiver of consequential damages, but not direct damages. The General Contractor then hired Gamma USA, Inc. as a subcontractor (Subcontractor) under a trade contract for curtainwall and façade work. The subcontract incorporated the CMA, made time of the essence, and provided that the Subcontractor would be liable for direct and consequential damages. It also stated that the owner's delay damages would be liquidated in the same manner as under the CMA, with the Subcontractor's liability for liquidated damages capped at $3.6 million. After Gamma sued for nonpayment and breach, the General Contractor and the Owner entered into an amended liquidating agreement so the General Contractor could assert a pass-through counterclaim on the Owner's behalf for damages allegedly caused by the Subcontractor's breaches.

Lower Court Decision

Supreme Court, New York County, granted Gamma's motion to dismiss the counterclaim to the extent of limiting recovery to the $3.6 million liquidated damages cap. The court reasoned that the counterclaim sought only the Owner's damages, not the General Contractor's independent damages, and concluded that under the CMA the Owner had waived recovery of damages other than liquidated damages from the General Contractor. Based on that reading, it held that all damages sought through the pass-through counterclaim were capped at $3.6 million.

Appellate Division Reversal

The Appellate Division modified the order. It agreed that the counterclaim was purely a pass-through claim for the Owner's losses and that the relevant contracts had to be read together. However, it held that the trial court read the contracts too broadly. The $3.6 million cap in the subcontract applied only to the Owner's delay damages. The CMA waived only consequential damages, not all non-liquidated damages. Therefore, the counterclaim could proceed for the Owner's direct damages, but not for consequential damages and not for delay damages exceeding the $3.6 million cap.

Legal Significance

The decision clarifies that in construction pass-through claims, a liquidating agreement does not expand or alter the underlying measure of damages available under the governing contracts. Courts must distinguish among liquidated delay damages, consequential damages, and direct damages. A contractual liquidated damages cap tied to delay applies only to delay-based losses unless the contract clearly says otherwise, and a waiver of consequential damages does not eliminate direct damages claims.

🔑 Key Takeaway

A subcontractor's contractual cap on liquidated delay damages does not automatically cap every type of owner loss asserted through a pass-through claim; unless the contracts clearly provide otherwise, direct damages may still be recovered, while consequential damages remain barred if waived.