Attorneys and Parties

Elmont Fire District
Defendant-Appellant
Attorneys: Steven E. Cohen

Custom Crafted Management Solutions, Inc.
Plaintiff-Respondent
Attorneys: Jay Edmund Russ, Ira Levine

Brief Summary

Issue

Public contracting with a fire district and the strict six-month notice-of-claim requirement for contract disputes, including when a contractor’s claim accrues for payment nonperformance.

Lower Court Held

The Supreme Court, Nassau County, denied the motion to dismiss, finding questions of fact existed as to when the causes of action accrued.

What Was Overturned

The Appellate Division reversed and granted dismissal under CPLR 3211(a) for failure to serve a timely notice of claim.

Why

Under Town Law § 180 [no action may be maintained against a fire district on a contract unless a written verified claim is filed with the district secretary within six months after accrual], the claims accrued on January 31, 2023 when payment demanded became due and was not made. The notice of claim served in October 2023 was therefore untimely, requiring dismissal. The court granted dismissal pursuant to CPLR 3211(a) [rule authorizing pre-answer motion to dismiss].

Background

Custom Crafted Management Solutions, Inc. (plaintiff) is the assignee of four vendors—Cascade Information Systems, Inc. (CIS), Atlantic Pacific Tech, Inc. (APT), Superior Integrated Solutions, Inc. (SIS), and Askdecom Computer Solutions, Inc. (ACS)—that contracted separately with the Elmont Fire District between 2017 and 2020 for computer-related services and equipment. On December 27, 2022, plaintiff issued four invoices alleging breach and demanding the full contract amounts, due January 31, 2023. Plaintiff’s notice of claim was allegedly hand-delivered to the district’s secretary on October 2, 2023 and mailed on October 10, 2023. Plaintiff commenced suit on March 3, 2024 seeking the contract balances, interest, legal fees, and costs. The District moved to dismiss, arguing the notice of claim was not served within six months of accrual as required by Town Law § 180.

Lower Court Decision

By order entered October 1, 2024, the Supreme Court, Nassau County, denied the motion, holding there were factual issues concerning the accrual date of the causes of action.

Appellate Division Reversal

Reversed on the law. The Appellate Division held the claims accrued on January 31, 2023, when the demanded payments became due and were not made, at which point the plaintiff should have viewed its claims as rejected. Because the notice of claim was not served until October 2023, it was untimely under Town Law § 180, a condition precedent to suit. The court therefore granted the District’s CPLR 3211(a) motion and dismissed the complaint.

Legal Significance

The decision reinforces that, in contract disputes with fire districts, strict compliance with Town Law § 180’s six-month verified claim filing requirement is a condition precedent that courts cannot waive. Contractor claims accrue upon actual or constructive rejection—here, when payment became due and was not made—triggering the six-month period. Failure to timely serve the notice results in dismissal at the pleading stage under CPLR 3211(a).

🔑 Key Takeaway

For contracts with a fire district, the six-month notice-of-claim clock starts when payment is due and not made; missing that deadline is fatal and will lead to dismissal.